Use wechat to scan the QR code < / P > < p > to share with friends and circle of friends < / P > < p > Beijing News shell financial news (reporter) On March 11, shell financial reporter learned from the EIA information disclosure platform of Shanghai construction project that the second phase a of Tesla Shanghai Super factory project (phase I) was completed on March 9, and the commissioning was conducted from March 10 to March 30. The acceptance period of the project is expected to be from March 10 to March 30. < / P > < p > according to the plan, < a target = "_ blank" href=" https://news.163.com/news/search?keyword=%E7%89%B9%E6%96%AF%E6%8B%89 "> Tesla < / a > Super factory project (phase I) is completed in two phases. The first phase has been completed in September 2019, with a planned annual output of 150000 < a target ="_ blank" href=" https://news.163.com/news/search?keyword=Model%203 ">Model 3。 The environmental protection report shows that the second stage is divided into two stages a and B for implementation and acceptance, in which the construction of stage a was officially started on February 1 and completed on March 9, taking only 37 days. < / P > < p > according to the EIA report, in the second phase of Tesla Tesla super factory project (phase I), the construction content of phase A is to increase the production capacity of model 3 in the first phase from the original 150000 vehicles by increasing the number of workers, prolonging the production time and improving the equipment start-up rate, but the final increase quantity is not disclosed. < / P > < p > with the completion of phase A and the start of commissioning, this means that Tesla's model 3 capacity in Shanghai Super factory will start to increase. < / P > < p > according to the information released by Tesla in the fourth quarter of last year, the company has plans to increase the production capacity of Shanghai Super factory from 250000 to 450000 within this year. In phase B, Tesla China will expand its existing new car pre start project on the basis of the built test equipment to form two complete production lines, meeting the requirements of < a target = "_ blank" href=" https://news.163.com/news/search?keyword=%E6%96%B0%E8%83%BD%E6%BA%90%E8%BD%A6 "> new energy vehicles < / a > vehicle production demand. < p > < p > according to the reporter of shell finance, the construction of Tesla's new car pre start project started in September last year, and it is planned to complete and start commissioning on March 31 this year. < / P > < p > in addition, in the near future, Shanghai will sell a piece of industrial land located in the port heavy equipment industrial zone of the free trade zone. The land access industry is similar to the manufacturing of new energy vehicles. The market generally believes that this piece of land near the Shanghai Super factory of Tesla is to prepare for the expansion of Tesla. < / P > < p > Tesla's revenue in the Chinese market last year reached US $6.662 billion, up 123.6% year on year, and model 3 and model y, two models made in China, are warmly sought after by Chinese consumers. According to the figures released by the passenger Federation, in February this year, Tesla sold 18318 electric vehicles in China, second only to < a target = "_ blank" href=" https://news.163.com/news/search?keyword=%E4%B8%8A%E6%B1%BD "> SAIC < / a > GM Wuling.